Construction Updates

Complete

Night works will resume from Monday 4 January 2021 and will continue through to Thursday 31 January 2021 for five

Complete

On intermittent nights until 29 January 2021 access to the CBD will be via Elizabeth St for southbound traffic on

Complete

A Temporary Gantry will be installed over the Clem Jones Promenade spanning between the River and the Bridge compound in

Complete

Materials and equipment required for piling will be lifted from the barge on the Brisbane River over the Clem Jones

Complete

Current night works onsite will continue until Thursday 17 December 2020 for five nights a week. Night works are required

Complete

For safety reasons a tower crane and chiller installation has been scheduled for both Saturday 5 and Sunday 6 December

Complete

Extended: For six nights over a one month period from Wednesday 4 November 2020 access to the CBD will be

Complete

Tower crane installation and dismantle at the Queen’s Wharf site on Saturday 21 and Sunday 22 November 2020. This activity

Complete

Starting Monday 12 October 2020 through to Thursday 12 November 2020, for five nights a week, night works will be

Complete

Starting Monday 12 October 2020 through to Thursday 12 November 2020, for five nights a week, night works will be

Complete

Night work will occur on Monday 9 November and Tuesday 10 November, for two nights only, while a 250 tonne

Complete

Night works: For five nights over a two-week period from Monday 19 October 2020 access to the CBD will be

Complete

From 28 September to 6 October 2020 night works will occur adjacent to the Bicentennial Bikeway for a 100 metre

Complete

Early works to investigate ground conditions are in sections adjacent to the Bicentennial Bikeway, which may require some temporary reductions

Complete

Night work will occur on Tuesday 1 September and Wednesday 2 September, for two nights only, while a 250 tonne

Complete

To create a safe work zone, a section of the Bicentennial Bikeway, adjacent to the Finger Wharves, will be intermittently

Complete

From 8 September to 11 September 2020 night works will occur adjacent to the Bicentennial Bikeway. When: Night works along

Complete

To create a safe work zone, a section of the Bicentennial Bikeway, adjacent to the Finger Wharves, will be intermittently

Complete

Early works to investigate ground conditions are in sections adjacent to the Bicentennial Bikeway, which may require some temporary reductions

Complete

From Sunday 5 July 2020 night work will occur along Margaret Street and then George Street temporarily affecting traffic and